Let's say I have a Gantt Chart in Visio. Can I make a flowchart in another Visio page that is linked tosome tasks in the Gantt Chart? For example, say I have a Gantt Chart with the following tasks (and subtasks):
- Issue parts list
- define drawings
- combine drawing numbers
- Make assembly 1
- Make assembly 2
- assemble FWD section
- flow check
- assemble AFT section
- Dimensional inspections of assemblies 1 and 2 together
- Make assembly 3
- Make final assembly
And I would like the flowchart to be:
Issue parts list ---> Make assembly 1 ---> Make assembly 2 ---> Make assembly 3 ---> Make final assembly
Can I do that?
In such a way that if I added another task in the Gantt Chart that I would also like to show in the flowchart I could do so by just "refreshing" the flowchart? For example, assume I add "Send assembly 1 to vendor for coat application" between "Make assembly 1" and "Make assembly 2", and I wanted this new task to be in the flowchart. Can I "refresh" the flowchart so it now shows the following:
Issue parts list ---> Make assembly 1 ---> Send assembly 1 to vendor for coat application ---> Make assembly 2 ---> Make assembly 3 ---> Make final assembly
I'm new to Visio. I normally use Excel and Powerpoint, but I dont know of a way of linking a flowchart with a Gantt chart. If there is such a way in Excel, feel free to let me know, too :)
I appreciate the help!!
-Tanzanite